Project Completion Certificate (Ground Water)
Scheme ID: 20059003 Name of Scheme: BEERHIJOR JJM No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 3540 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Jul-2024 Actual Date of Completion (Capex): 25-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24M/297M BEERHIJOR 27.25795 79.786735
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 45.00M³/43M BEERHIJOR 27.25795 79.786735
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225kl/14M BEERHIJOR 27.25795 79.786735
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 100 0.002
2 DI PIPE 150 0.028
3 DI PIPE 200 0.003
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 75 2.291
2 HDPE PIPE PN:-6 90 2.027
3 HDPE PIPE PN:-6 110 0.541
4 HDPE PIPE PN:-6 125 0.100
5 HDPE PIPE PN:-6 63 4.852
6 HDPE PIPE PN:-6 140 0.760
7 HDPE PIPE PN:-6 160 0.00
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 0.130
HSC Connection
Sno. Total Nos.
1 535
Other Details
2.40
0.00
2.43
24-Sep-2025
25-Sep-2025