Project Completion Certificate (Ground Water)
Scheme ID: 20059032 Name of Scheme: KALYANI (GOGP) JJM No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 4950 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Sep-2024 Actual Date of Completion (Capex): 27-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 22M/125M KALYANI 27.572714 80.269716
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 62.4M³/45M KALYANI 27.572714 80.269716
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300KL/16M KALYANI 27.572714 80.269716
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 0.003
2 DI PIPE 200 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 4.366
2 HDPE PIPE PN:-6 75 2.627
3 HDPE PIPE PN:-6 90 1.937
4 HDPE PIPE PN:-6 110 0.218
5 HDPE PIPE PN:-6 125 0.613
6 HDPE PIPE PN:-6 140 0.00
7 HDPE PIPE PN:-6 160 0.00
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 4.199
HSC Connection
Sno. Total Nos.
1 879
Other Details
3.27
0.00
3.46
26-Jul-2025
25-Sep-2025