Project Completion Certificate (Ground Water)
Scheme ID: 20066058 Name of Scheme: PINDARA KARNAI WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 5376 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Aug-2024 Actual Date of Completion (Capex): 26-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 MS PIPE 300MM - 150MM 16MTR / 78.5 PINDRA KARNAI 26.376905 81.768603
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 750 / 52MTR PINDRA KARNAI 26.376905 81.768603
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 225KL / 14MTR PINDRA KARNAI 26.376905 81.768603
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 .021
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63MM TO 200MM 200 10.225
HSC Connection
Sno. Total Nos.
1 677
Other Details
3.72
0.00
3.68
30-Oct-2025
04-Jan-2026