Project Completion Certificate (Ground Water)
Scheme ID: 20066503 Name of Scheme: SEMRAUTA VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 13
Total Population Covered: 1717 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Dec-2023 Actual Date of Completion (Capex): 06-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL - 1 13.68/74.84 SEMRAUTA 26.4558362 81.406529
2 TUBEWELL-2 15.2/56.62 SEMRAUTA 26.452320 81.403953
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE -1 775 LPM/54M SEMRAUTA 26.4558362 81.406529
2 SUBMERSIBLE-2 775 LPM/56 M SEMRAUTA 26.452320 81.403953
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 450/18 SEMRAUTA 26.4558362 81.406529
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.817
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 6.823
2 HDPE 110 2.407
3 HDPE 125 0.363
4 HDPE 63 12.759
5 HDPE 140 2.532
6 HDPE 160 0.517
7 HDPE 200 0.806
HSC Connection
Sno. Total Nos.
1 1226
Other Details
7.15
0.00
7.10
06-Sep-2024
07-Dec-2024