Project Completion Certificate (Ground Water)
Scheme ID: 20067202 Name of Scheme: KARAULI LATHAUR Water Supply Scheme No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 3110 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Feb-2024 Actual Date of Completion (Capex): 19-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of Borewell Assembly 24.12 M/ 62.30 M Kroli Lathori 26.368226 83.028793
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP submersible pump set 650LPM/44M Karoli Lathori 26.368226 83.028793
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 200 KL/ 14 M Karoli Lathori 26.368226 83.028793
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI- K7 150 0.040 0.018
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 0.773
2 HDPE Pipe PN-6: Class PE-100 75 0.879
3 HDPE Pipe PN-6: Class PE-100 63 9.082
4 HDPE Pipe PN-6: Class PE-100 110 0.377
5 HDPE Pipe PN-6: Class PE-100 125 0.284
6 HDPE Pipe PN-6: Class PE-100 140 0.280
7 HDPE Pipe PN-6: Class PE-100 160 0.187
8 HDPE Pipe PN-6: Class PE-100 180 0.587
HSC Connection
Sno. Total Nos.
1 605
Other Details
2.56
2.55
2.55
07-Apr-2026
08-Apr-2026