Project Completion Certificate (Ground Water)
Scheme ID: 20069410 Name of Scheme: MANGRAWA WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 9
Total Population Covered: 2310 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 05-Feb-2024 Actual Date of Completion (Capex): 04-Mar-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 12.00/71.30 MANGRAWA 26.138946 82.411254
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump-1 490LPM/43M MANGRAWA 26.138946 82.411254
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150KL/12M MANGRAWA 26.138946 82.411254
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 100 0.012
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE-PN-6 , PE-100 63 8.817
2 HDPE-PN-6 , PE-100 75 2.293
3 HDPE-PN-6 , PE-100 90 1.170
4 HDPE-PN-6 , PE-100 110 1.063
5 HDPE-PN-6 , PE-100 140 1.280
6 HDPE-PN-6 , PE-100 160 0.579
HSC Connection
Sno. Total Nos.
1 350
Other Details
2.09
0.00
2.06
18-Apr-2026
01-May-2026