| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20073324 | Name of Scheme: Niwari Kalan | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 6125 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 15-Mar-2024 | Actual Date of Completion (Capex): 25-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 153.88 MTR/ 33.03 MTR | NIWARI KALAN | 26.65348* | 79.288406* |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 71.42 M^3 / 49 MTR | NIWARI KALAN | 26.65348* | 79.288406* |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 350 KL /16 MTR | NIWARI KALAN | 26.65348* | 79.288406* |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.043 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 9.854 | |
| 2 | HDPE | 110 | 2.892 | |
| 3 | HDPE | 140 | 1.757 | |
| 4 | HDPE | 180 | 2.577 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 972 |