| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20074587 | Name of Scheme: DHARAMPUR MVS | No. of Villages: 4 | No. of Habitation Covered: 6 |
| Total Population Covered: 4069 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 30-May-2025 | Actual Date of Completion (Capex): 02-Jul-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 27.0 M/ 162.32 M | DHARAMPUR | 27.60757 | 79.31940 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | PUMPS | 850 LPM/ 65 M | DHARAMPUR | 27.60757 | 79.31940 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 250 KL / 18 M | DHARAMPUR | 27.60757 | 79.31940 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE/ K7 | 150 | .025 | COMPLETE |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.782 | COMPLETE |
| 2 | HDPE | 63 | 9.501 | COMPLETE |
| 3 | HDPE | 110 | 1.045 | COMPLETE |
| 4 | HDPE | 140 | 1.887 | COMPLETE |
| 5 | HDPE | 160 | 1.327 | COMPLETE |
| 6 | HDPE | 180 | .524 | COMPLETE |
| 7 | HDPE | 200 | .024 | COMPLETE |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 692 |