Project Completion Certificate (Ground Water)
Scheme ID: 20077495 Name of Scheme: KAPERKATKA WSS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1951 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 25-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 15.00/96.00 KAPERKATKA 27.980439 79.846007
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT PUMP - 1 23.40 M3 / 45 M KAPERKATKA 27.980439 79.846007
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT - 1 100 KL - 14 M KAPERKATKA 27.980435 79.84012
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI - K7 100 0.040
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6 KG 63 2.072
2 HDPE / 6 KG 75 0.381
3 HDPE / 6 KG 90 0.099
4 HDPE / 6 KG 110 0.101
5 HDPE / 6 KG 140 0.397
HSC Connection
Sno. Total Nos.
1 345
Other Details
1.40
0.00
1.40
24-Sep-2024
06-Dec-2024