| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20077607 | Name of Scheme: GAUPUR BIRIYA RASOOLABAD | No. of Villages: 5 | No. of Habitation Covered: 9 |
| Total Population Covered: 4319 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 14-Mar-2024 | Actual Date of Completion (Capex): 18-Feb-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 39.09/227.25 | GAUPUR BIRIYA RASOOLABAD | 26.591721 | 79.816054 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 1050/66 | GAUPUR BIRIYA RASOOLABAD | 26.591721 | 79.816054 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 300/18 | GAUPUR BIRIYA RASOOLABAD | 26.591721 | 79.816054 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI/K7 | 150 | 0.008 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 9.236 | |
| 2 | HDPE | 90 | 4.454 | |
| 3 | HDPE | 110 | 1.337 | |
| 4 | HDPE | 125 | 0.700 | |
| 5 | HDPE | 140 | 0.553 | |
| 6 | HDPE | 160 | 0.373 | |
| 7 | HDPE | 180 | 1.099 | |
| 8 | HDPE | 200 | 0.912 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 774 |