Project Completion Certificate (Ground Water)
Scheme ID: 20078881 Name of Scheme: udi No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2200 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 15-Mar-2024 Actual Date of Completion (Capex): 25-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 26.82 Mtr/ 126.54 Mtr UDI 26.701661* 78.949045*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 27.60 M^3/ 52 Mtr UDI 26.701661* 78.949045*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 125 KL /12 MTR UDI 26.701661* 78.949045*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 80 0.045
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.256
2 HDPE 75 0.728
3 HDPE 90 2.450
4 HDPE 110 0.972
5 HDPE 140 0.560
6 HDPE 180 0.714
HSC Connection
Sno. Total Nos.
1 465
Other Details
1.69
2.25
2.25
25-Jun-2024
26-Jun-2024