Project Completion Certificate (Ground Water)
Scheme ID: 20082414 Name of Scheme: KUWARPURWA GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 7
Total Population Covered: 3170 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 08-Aug-2025 Actual Date of Completion (Capex): 29-Jan-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Slotted Pipe 150mm 23.9 TW 26.187669 83.7645623
2 Plain Pipe 150mm 81.05 TW 26.187669 83.7645623
3 Housing Pipe 45.1 TW 26.187669 83.7645623
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Solar Submersible Pump 700/44 TW 26.187669 83.7645623
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zinc Tank 225/16 OHT 26.187669 83.7645623
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 13.69
2 HDPE Pipe PN-6: Class PE-100 90 0.23
3 HDPE Pipe PN-6: Class PE-100 110 0.91
4 HDPE Pipe PN-6: Class PE-100 140 1.01
HSC Connection
Sno. Total Nos.
1 440
Other Details
2.65
2.02
2.10
17-Sep-2025
29-Jan-2026