Project Completion Certificate (Ground Water)
Scheme ID: 20082426 Name of Scheme: RO- GAURIDIH GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 4 No. of Habitation Covered: 12
Total Population Covered: 2510 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 08-Aug-2024 Actual Date of Completion (Capex): 06-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Slotted Pipe 150mm 18 TW 26.1157322 83.5255182
2 Plain Pipe 150mm 28.43 TW 26.1157322 83.5255182
3 Housing Pipe 200mm 54 TW 26.1157322 83.5255182
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Solar Submersible Pump 550/44 TW 26.1157322 83.5255182
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zinc Tank 175/16 OHT 26.1157322 83.5255182
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 11.05
2 HDPE Pipe PN-6: Class PE-100 75 1.01
3 HDPE Pipe PN-6: Class PE-100 90 1.17
4 HDPE Pipe PN-6: Class PE-100 110 0.34
5 HDPE Pipe PN-6: Class PE-100 125 0.14
6 HDPE Pipe PN-6: Class PE-100 160 0.24
HSC Connection
Sno. Total Nos.
1 381
Other Details
2.41
1.72
1.88
15-Aug-2025
06-Nov-2025