| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20082989 | Name of Scheme: CHIKANIADEEH & BELAULI GOV WSS | No. of Villages: 4 | No. of Habitation Covered: 7 |
| Total Population Covered: 6405 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 04-Apr-2023 | Actual Date of Completion (Capex): 28-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 133.42(m)/30.04(m) | Belauli | 26.915391 | 83.205443 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 890 LPM/45(M) | Belauli | 26.915333 | 83.205422 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Over Head Tank | 250kl/14m | Belauli | 26.915142 | 83.205292 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI/K-7 | 150 | 0.02285 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PE-100 PN 6/HDPE | 63 | 13.599 | |
| 2 | PE-100 PN 6/HDPE | 75 | 6.638 | |
| 3 | PE-100 PN 6/HDPE | 90 | 2.505 | |
| 4 | PE-100 PN 6/HDPE | 110 | 1.656 | |
| 5 | PE-100 PN 6/HDPE | 140 | 0.759 | |
| 6 | PE-100 PN 6/HDPE | 160 | 0.484 | |
| 7 | PE-100 PN 6/HDPE | 180 | 0.628 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 956 |