| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20084771 | Name of Scheme: RANIPUR KAYSTH WSS | No. of Villages: 2 | No. of Habitation Covered: 6 |
| Total Population Covered: 2550 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 22-Mar-2024 | Actual Date of Completion (Capex): 21-Mar-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 20.00/50.50 | RANIPUR KAYSTH | 26.164059 | 82.380481 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT Pump-1 | 542LPM/45M | RANIPUR KAYSTH | 26.164059 | 82.380481 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 150KL/10M | RANIPUR KAYSTH | 26.164059 | 82.380481 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI Pipe K-7 | 100 | 0.020 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE-PN-6 , PE-100 | 63 | 9.654 | |
| 2 | HDPE-PN-6 , PE-100 | 75 | 1.483 | |
| 3 | HDPE-PN-6 , PE-100 | 90 | 1.381 | |
| 4 | HDPE-PN-6 , PE-100 | 110 | 0.628 | |
| 5 | HDPE-PN-6 , PE-100 | 140 | 0.329 | |
| 6 | HDPE-PN-6 , PE-100 | 160 | 0.132 | |
| 7 | HDPE-PN-6 , PE-100 | 200 | 0.018 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 430 |