Project Completion Certificate (Ground Water)
Scheme ID: 20085253 Name of Scheme: RO BIBIPUR UDHARAN GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 6
Total Population Covered: 2020 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 08-Aug-2024 Actual Date of Completion (Capex): 22-Apr-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Slotted Pipe 150mm 14 TW 25.8881806 83.733219
2 Plain Pipe 150mm 29.3 TW 25.8881806 83.733219
3 Housing Pipe Slotted 200mm 6 TW 25.8881806 83.733219
4 Housing Pipe Plain 200mm 48 TW 25.8881806 83.733219
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Solar Submersible Pump 450/40 TW 25.8881806 83.733219
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zinc Tank 150/12 OHT 25.8881806 83.733219
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 3.56
2 HDPE Pipe PN-6: Class PE-100 75 1.73
3 HDPE Pipe PN-6: Class PE-100 90 0.5
4 HDPE Pipe PN-6: Class PE-100 110 0.43
5 HDPE Pipe PN-6: Class PE-100 140 0.104
HSC Connection
Sno. Total Nos.
1 361
Other Details
1.80
1.43
1.45
14-Mar-2026
22-Apr-2026