Project Completion Certificate (Ground Water)
Scheme ID: 20086982 Name of Scheme: RUNABE WSS No. of Villages: 4 No. of Habitation Covered: 6
Total Population Covered: 3190 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 18-Jan-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of Borewell Assembly 21.15 M/ 74.04 M Durgechitpur 26.330991 83.088207
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP Submersible Pump 670 LPM/ 45M Durgechitpur 26.330991 83.088207
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 200 KL/ 14 M Durgechitpur 26.330991 83.088207
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI- K7 150 0.0275
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 1.448
2 HDPE Pipe PN-6: Class PE-100 75 2.108
3 HDPE Pipe PN-6: Class PE-100 63 7.535
4 HDPE Pipe PN-6: Class PE-100 110 1.277
5 HDPE Pipe PN-6: Class PE-100 140 0.487
6 HDPE Pipe PN-6: Class PE-100 160 1.260
7 HDPE Pipe PN-6: Class PE-100 180 1.273
HSC Connection
Sno. Total Nos.
1 699
Other Details
2.91
2.90
2.90
19-Jun-2026
20-Jun-2026