| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20087729 | Name of Scheme: NAGLA SALEHADI | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1710 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 15-Mar-2024 | Actual Date of Completion (Capex): 15-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18.15 Mtr /148.35 Mtr | NAGLA SALEDHI | 26.664379* | 79.246551* |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 21 M^3/53 Mtr | NAGLA SALEDHI | 26.664379* | 79.246551* |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100 KL/12 Mtr | NAGLA SALEDHI | 26.664379* | 79.246551* |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 80 | 0.031 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 2.234 | |
| 2 | HDPE | 75 | 0.811 | |
| 3 | HDPE | 90 | 1.451 | |
| 4 | HDPE | 110 | 1.173 | |
| 5 | HDPE | 140 | 0.820 | |
| 6 | HDPE | 160 | 0.518 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 347 |