Project Completion Certificate (Ground Water)
Scheme ID: 20094144 Name of Scheme: KUSUMBHI & JAGATPUR Water Supply Scheme No. of Villages: 2 No. of Habitation Covered: 14
Total Population Covered: 5795 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Apr-2024 Actual Date of Completion (Capex): 12-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL-1 15.06/67.70 KUSUMBHI & JAGATPUR 26.558972 81.362783
2 TUBEWELL-2 16.05/62.66 KUSUMBHI & JAGATPUR 26.568590 81.375858
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 625 LPM/ 55 M KUSUMBHI & JAGATPUR 26.558972 81.362783
2 SUBMERSIBLE - 2 625 LPM/ 55 M KUSUMBHI & JAGATPUR 26.568590 81.375858
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350/20 KUSUMBHI & JAGATPUR 26.558972 81.362783
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.491
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 12.663
2 HDPE 90 5.459
3 HDPE 110 1.956
4 HDPE 125 0.354
5 HDPE 140 1.205
6 HDPE 160 0.547
7 HDPE 180 1.037
8 HDPE 200 3.150
HSC Connection
Sno. Total Nos.
1 910
Other Details
5.90
0.00
5.87
01-Mar-2025
02-Jun-2025