Project Completion Certificate (Ground Water)
Scheme ID: 20096713 Name of Scheme: PANDARWA KILA JJM No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 5910 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 08-Dec-2024 Actual Date of Completion (Capex): 13-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 30M/115M PANDRAWA KILA 27.654125 80.23425
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 69.6M³/43M PANDRAWA KILA 27.654125 80.23425
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350KL/14M PANDRAWA KILA 27.654125 80.23425
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 0.001
2 DI PIPE 200 0.036
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 5.934
2 HDPE PIPE PN:-6 75 5.148
3 HDPE PIPE PN:-6 90 1.797
4 HDPE PIPE PN:-6 110 0.498
5 HDPE PIPE PN:-6 125 1.151
6 HDPE PIPE PN:-6 140 0.00
7 HDPE PIPE PN:-6 160 0.128
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 0.380
HSC Connection
Sno. Total Nos.
1 1003
Other Details
3.52
0.00
3.49
12-Jun-2025
26-Sep-2025