Project Completion Certificate (Ground Water)
Scheme ID: 20096863 Name of Scheme: Rajpalpur No. of Villages: 2 No. of Habitation Covered: 6
Total Population Covered: 4990 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Mar-2022 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 27.01/163.03 Raipalpur 26.467479' 80.061089'
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 52.30/61 Raipalpur 26.467479' 80.061089'
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300/16 Raipalpur 26.467479' 80.061089'
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.030 As per Site
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 9.70 As per Site
2 HDPE 75 0.120 As per Site
3 HDPE 90 0.492 As per Site
4 HDPE 110 6.50 As per Site
5 HDPE 125 1.170 As per Site
6 HDPE 140 0.337 As per Site
7 HDPE 160 1.890 As per Site
8 HDPE 180 0.450 As per Site
HSC Connection
Sno. Total Nos.
1 725
Other Details
3.71
4.41
4.41
23-Mar-2024
24-Mar-2024