| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097148 | Name of Scheme: Mundera water supply system | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 1920 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 21-Oct-2024 | Actual Date of Completion (Capex): 30-Oct-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 18/150 | Mundera | 26.5 | 83.53 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 24/39 | Mundera | 26.5 | 83.53 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Overhead Tank-1 | 100/12 | Mundera | 26.5 | 83.53 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.017 | Laying Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 7.25 | Laying Completed |
| 2 | HDPE | 90 | 0.19 | Laying Completed |
| 3 | HDPE | 110 | 0.22 | Laying Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 313 |