Project Completion Certificate (Ground Water)
Scheme ID: 20097816 Name of Scheme: GOPIYAGANJ No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1835 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 02-Apr-2024 Actual Date of Completion (Capex): 20-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 118 mtr/21.00 mtr GOPIYAGANJ 26.785137* 79.215553*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 24 M^3 /45 MTR GOPIYAGANJ 26.785137* 79.215553*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100 KL/ 16 MTR GOPIYAGANJ 26.785137* 79.215553*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DJ 100 0.0271
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 1.165
2 HDPE 75 1.130
3 HDPE 90 0.789
4 HDPE 110 0.256
5 HDPE 160 0.419
HSC Connection
Sno. Total Nos.
1 360
Other Details
1.40
1.72
1.72
20-Jul-2024
21-Jul-2024