Project Completion Certificate (Ground Water)
Scheme ID: 20098955 Name of Scheme: MOLANAPUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 5
Total Population Covered: 1505 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Oct-2024 Actual Date of Completion (Capex): 19-Jan-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Slotted Pipe 150mm 24.02 TW 26.0385281 83.4600444
2 Plain Pipe 150 mm 38 TW 26.0385281 83.4600444
3 Housing Pipe 200mm 42.04 TW 26.0385281 83.4600444
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Solar Submersible Pump 350/45 TW 26.0385281 83.4600444
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zinc Tank 100/14 OHT 26.0385281 83.4600444
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 9.06
2 HDPE Pipe PN-6: Class PE-100 75 1.34
3 HDPE Pipe PN-6: Class PE-100 90 0.67
4 HDPE Pipe PN-6: Class PE-100 110 0.74
5 HDPE Pipe PN-6: Class PE-100 125 0.47
6 HDPE Pipe PN-6: Class PE-100 140 0.27
7 HDPE Pipe PN-6: Class PE-100 160 0.21
HSC Connection
Sno. Total Nos.
1 309
Other Details
2.23
1.73
1.98
25-Dec-2025
19-Jan-2026