| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20099333 | Name of Scheme: Jahangirpur | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 4381 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2023 |
| Date of Completion (As per Contract): 31-Dec-2023 | Actual Date of Completion (Capex): 08-Feb-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 7/66.33 | JAHANGIRPUR | 28.1833° | 77.7167° |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 400/73 | JAHANGIRPUR | 28.1833° | 77.7167° |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 125/16 | JAHANGIRPUR | 28.1833° | 77.7167° |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.020 | COMPLETED |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 10.50 | COMPLETED |
| 2 | HDPE | 90 | 0.993 | COMPLETED |
| 3 | HDPE | 110 | 1.37 | COMPLETED |
| 4 | HDPE | 140 | 0.152 | COMPLETED |
| 5 | HDPE | 160 | 1.389 | COMPLETED |
| 6 | HDPE | 180 | 0.363 | COMPLETED |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 890 |