Project Completion Certificate (Ground Water)
Scheme ID: 20099647 Name of Scheme: Girdaun No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 3446 Base Year: 2023 Intermediate Year: 2038 Design Year: 2023
Date of Completion (As per Contract): 17-Jan-2023 Actual Date of Completion (Capex): 16-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 16/134.52 GIRDAUN 26.269928 79.911652
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 7.497
2 HDPE PIPE 75 0.235
3 HDPE PIPE 90 0.965
4 HDPE PIPE 110 2.973
5 HDPE PIPE 125 0.996
6 HDPE PIPE 140 0.072
7 HDPE PIPE 160 0.095
8 HDPE PIPE 180 0.047
HSC Connection
Sno. Total Nos.
1 687
Other Details
2.67
0.00
3.12
02-Mar-2025
03-Mar-2025