| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20100172 | Name of Scheme: KUAN DANDA GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1330 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 20-May-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 12.00/84.60 | KAUN DANDA | 27.959908 | 79.769538 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT Pomp -1 | 16.80 M3 / 45 M | KAUN DANDA | 27.959908 | 79.769538 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT - 1 | 75 KL - 12 M | KAUN DANDA | 27.959704 | 79.769338 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI - K7 | 100 | 0.020 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE / 6KG | 63 | 1.368 | |
| 2 | HDPE / 6KG | 75 | 1.130 | |
| 3 | HDPE / 6KG | 90 | 0.563 | |
| 4 | HDPE / 6KG | 110 | 0.152 | |
| 5 | HDPE / 6KG | 140 | 0.048 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 266 |