| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20100805 | Name of Scheme: PATTISHAH | No. of Villages: 1 | No. of Habitation Covered: 11 |
| Total Population Covered: 5880 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 18-Mar-2024 | Actual Date of Completion (Capex): 30-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 15/123.0 | PATTI SHAH | 25'.935757'N | 81.179292"8 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | submersible | 500/60 | PATTI SHAH | 25'.935757'N | 81.179292"8 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT.1 | 175/14 | PATTI SHAH | 25'.935757'N | 81.179292"8 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.t. K-9 | 80 | 0.03050 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 200 | 0.4725 | |
| 2 | HDPE | 140 | 1.7136 | |
| 3 | HDPE | 125 | 0.4787 | |
| 4 | HDPE | 110 | 1.6924 | |
| 5 | HDPE | 90 | 2.230 | |
| 6 | HDPE | 75 | 1.4985 | |
| 7 | HDPE | 63 | 9.7337 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1190 |