Project Completion Certificate (Ground Water)
Scheme ID: 20101994 Name of Scheme: AINDHI WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 27
Total Population Covered: 9820 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 28-Dec-2024 Actual Date of Completion (Capex): 07-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 MS PIPE 300MM AND 150MM 58M/617.6M AINDHI 26.230028 81.608955
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 2064.01LPM/110M AINDHI 26.230028 81.608955
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 125KL/18M,500KL/16 AINDHI 26.230028 81.608955
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150MM 200 0.525
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63MM TO 250MM 250 70.542
HSC Connection
Sno. Total Nos.
1 1650
Other Details
11.16
0.00
11.14
12-Sep-2025
22-Dec-2025