Project Completion Certificate (Ground Water)
Scheme ID: 20102287 Name of Scheme: HARKISHANPUR WSS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1963 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 14-Jan-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 24.08 /146.46 Harkishanpur 29.274187 78.764782
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 380/49 Harkishanpur 29.274187 78.764782
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 125/12 Harkishanpur 29.274187 78.764782
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI- K7 100 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 3.344
2 HDPE PIPE 75 0.305
3 HDPE PIPE 110 0.100
4 HDPE PIPE 125 0.130
HSC Connection
Sno. Total Nos.
1 275
Other Details
1.54
0.00
1.69
14-Jul-2026
15-Jul-2026