Project Completion Certificate (Ground Water)
Scheme ID: 20102310 Name of Scheme: Rasolpur Kasba WSS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2029 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 24-Jan-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBE WELL 30.03/125.07 Rasoolpur Kasba 29.134217 78.624442
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 450/50 Rasoolpur Kasba 29.134217 78.624442
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 125/12 Rasoolpur Kasba 29.134217 78.624442
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 100 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 1.687
2 HDPE PIPE 75 0.789
3 HDPE PIPE 90 0.558
4 HDPE PIPE 110 0.234
5 HDPE PIPE 125 0.255
HSC Connection
Sno. Total Nos.
1 405
Other Details
1.66
0.00
1.78
24-Jul-2026
25-Jul-2026