| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20102358 | Name of Scheme: UPLARASI VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1729 | Base Year: 2019 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 28-Jul-2023 | Actual Date of Completion (Capex): 30-Jul-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 99M/21M | Uplarsi | 28.561268, | 77.628944 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submercible | 370LPM/55M | Uplarsi | 28.561268, | 77.628944 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 125 KL/12M | Uplarsi | 28.561268, | 77.628944 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.021 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.635 | |
| 2 | HDPE | 75 | 0.503 | |
| 3 | HDPE | 90 | 0.481 | |
| 4 | HDPE | 110 | 0.093 | |
| 5 | HDPE | 125 | 0.161 | |
| 6 | HDPE | 160 | 0.396 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 316 |