Project Completion Certificate (Ground Water)
Scheme ID: 8359384 Name of Scheme: Chiruhuli No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3315 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 29-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 21.0 M / 107.07 M Chiruhuli 26.483716* 79.467982*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible (47.41 M3/Hr.) / 40 M Chiruhuli 26.483716* 79.467982*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225 Kl / 12 M Chiruhuli 26.48372* 79.467948*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 150 0.0165
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.41
2 HDPE 75 0.648
3 HDPE 90 0.567
4 HDPE 110 0.34
5 HDPE 160 0.05
HSC Connection
Sno. Total Nos.
1 739
Other Details
2.79
2.16
2.16
04-Jan-2025
05-Jan-2025