Check List Form

      Purwa GOV (8135931)

Project Completion Plan


Minutes of Meeting Date - 06-Jan-2026

2 no of OHT are shown less then 75% and 2 nos of OHT are shown more then 150% because of over wastage of water by villagers but overall water supply shown 97% . All OHTs and CWRs are connected to SACDA.


Minutes of Meeting Date - 06-Jan-2026

1 no of OHT are shown less then 75% and 2 nos of OHT are shown more then 150% because of over wastage of water by villagers but overall water supply shown 132% . OHT 1 is shown only 44 LPCD because of campus is waret logged and for safety purpose water supply is through bypass system. All OHTs and CWRs are connected to SACDA.