Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38387 | 38011 | 99.02 |
| 2 | Pump House | 38387 | 37282 | 97.12 |
| 3 | OHT | 36445 | 35856/21315 | 98.38 |
| 4 | Distribution (Line Laying in Km.) | 450559 | 427200 | 94.82 |
| 5 | Solar Plant | 32838 | 29200 | 88.92 |
| 6 | HGJ Status | 72776 | 42577 | 58.50 |
| 7 | Comissioning of Village | 72776 | 47901 | 65.82 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 194482 | 193162 | 99.32 |