Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38387 38011 99.02
2 Pump House 38387 37282 97.12
3 OHT 36445 35856/21315 98.38
4 Distribution (Line Laying in Km.) 450559 427200 94.82
5 Solar Plant 32838 29200 88.92
6 HGJ Status 72776 42577 58.50
7 Comissioning of Village 72776 47901 65.82
8 ROAD DISMENTLING/RESTORATION(KM) 194482 193162 99.32