Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20016910 | PIDARI JJM | 203.91 | 202.67 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 19 | 19 | Yes | 0 | NA | No | 11108.00 | 13873.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Pindari | 455799 | Pindari | 126 | 126 | 100 | Har Gar Jal | Not Certified |
| 2 | Gorakhpur | Uruwa | Pindari | 455800 | Pindara | 38 | 38 | 100 | Har Gar Jal | Not Certified |
| 3 | Gorakhpur | Uruwa | Pindari | 455801 | Tiwaripur | 17 | 17 | 100 | Har Gar Jal | Not Certified |
| 4 | Gorakhpur | Uruwa | Pindari | 455802 | Bhatauli Khurd | 28 | 28 | 100 | Har Gar Jal | Not Certified |