Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Etah Power Mech Projects Ltd 20020367 NAGLA BARI 209.14 69.12 view more

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 0 1 21 21 Yes 0 NA No 7604.00 7956.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Etah Nidhauli Kalan Nagla Bari 399500 Bagla Bari 256 246 96 Work In Progress Not Certified
2 Etah Nidhauli Kalan Nagla Bari 399501 Paisai 129 124 96 Work In Progress Not Certified