Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20021854 | Noorpur Chibri Gram Panchayat Water Supply | 249.92 | 184.31 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 23 | Yes | 0 | NA | No | 6358.00 | 5937.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Alhepur | Noorpur Chibri | 387122 | Noorpur Chibri | 338 | 338 | 100 | Har Gar Jal | Certified |
| 2 | Bijnor | Alhepur | Noorpur Chibri | 387125 | BADSHAHPUR SHAHMO BILA AHATMAL | 56 | 56 | 100 | Har Gar Jal | Not Certified |