Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Bijnor Vindhya-GAJA (JV) 20021940 Mustafabad Gram Panchayat Water Supply 294.30 256.32 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 0 27 27 Yes 0 NA No 9932.00 9920.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Bijnor Netaur Mustafabad 386932 Mustafabad 212 204 96 Work In Progress Not Certified
2 Bijnor Netaur Mustafabad 386933 Chak Abdul Rahman 64 40 62 Work In Progress Not Certified
3 Bijnor Netaur Mustafabad 386934 Mimla 116 106 91 Work In Progress Not Certified
4 Bijnor Netaur Mustafabad 386935 Jamalpur 99 83 84 Work In Progress Not Certified