Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Larsen & Toubro Ltd | 20025440 | Uprahula-Barayal Water Supply Scheme | 352.75 | 249.68 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 25 | 25 | Yes | 0 | NA | No | 15191.00 | 15191.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Utraula | Barayal | 444238 | Barayal | 201 | 201 | 100 | Har Gar Jal | Not Certified |
| 2 | Balrampur | Utraula | Barayal | 444239 | Rajapur Mafi | 106 | 102 | 96 | Work In Progress | Not Certified |
| 3 | Balrampur | Utraula | Uprahula | 444240 | Uprahula | 131 | 131 | 100 | Har Gar Jal | Not Certified |
| 4 | Balrampur | Utraula | Uprahula | 444241 | Allipur Khurd | 37 | 35 | 95 | Work In Progress | Not Certified |
| 5 | Balrampur | Utraula | Uprahula | 444242 | Khajuha | 50 | 48 | 96 | Work In Progress | Not Certified |
| 6 | Balrampur | Utraula | Uprahula | 444243 | Rasoolpur Chand | 70 | 70 | 100 | Har Gar Jal | Not Certified |