Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Vindhya-GAJA (JV) | 20044249 | UMARIYA & JIGANIYAN JJM SCHEME | 317.34 | 247.67 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 14277.00 | 14376.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Nakaha | Jiganihan | 409306 | Jiganiyan | 319 | 319 | 100 | Har Gar Jal | Certified |
| 2 | Lakhimpur Kheri | Nakaha | Jiganihan | 409307 | Noudhan | 79 | 79 | 100 | Har Gar Jal | Certified |
| 3 | Lakhimpur Kheri | Nakaha | Umaria | 409309 | Umaria | 386 | 386 | 100 | Har Gar Jal | Not Certified |