Scheme Details
DISTRICT
Sambhal
AGENCY
PNC SPML- JV Moradabad
SCHEME ID
20050825
SCHEME NAME
RAWAN KHURD URF BIBIPUR
ESTIMATED COST
162.37
EXPENDITURE
65.67
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5396.00
Meter
Length Laid
5396.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Sambhal | RAYKHURD URF BIBIPUR | 389063 | RAWAN KHURD URF BIBIPUR | 445 | 349 | 78% | Work In Progress | Not Certified |