Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Bareilly NCC Ltd. 20053646 Nagla & Sirairi 330.14 159.16 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 23 23 Yes 0 NA No 12484.00 11540.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Bareilly Aalampur Jafrabad Nagla 403651 Nagla 268 268 100 Har Gar Jal Not Certified
2 Bareilly Aalampur Jafrabad Sirairi 403654 Sarari 285 285 100 Har Gar Jal Not Certified