Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20056762 | DEVLASPUR AND MANDUPUR VILLAGE WATER SUPPLY SCHEME | 347.63 | 186.35 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 21546.00 | 19741.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Dobhi | Mandupur | 471360 | Mandupur | 235 | 220 | 94 | Work In Progress | Not Certified |
| 2 | Jaunpur | Dobhi | Devlaspur | 471363 | Devlaspur | 228 | 217 | 95 | Work In Progress | Not Certified |
| 3 | Jaunpur | Dobhi | Devlaspur | 471364 | Balua Bijaipur | 113 | 105 | 93 | Work In Progress | Not Certified |