Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20058302 | GADDOPUR VILLAGE WATER SUPPLY SCHEME | 328.13 | 178.63 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | Yes | 0 | NA | No | 19705.00 | 17257.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Dharmapur | Dakhan | 470383 | Rajepur | 65 | 65 | 100 | Har Gar Jal | Not Certified |
| 2 | Jaunpur | Dharmapur | Baghandara | 470389 | Baghandara | 169 | 162 | 96 | Work In Progress | Not Certified |
| 3 | Jaunpur | Dharmapur | Gaddopur | 470413 | Kauwapar | 95 | 93 | 98 | Work In Progress | Not Certified |
| 4 | Jaunpur | Dharmapur | Gaddopur | 470414 | Gaddopur | 108 | 108 | 100 | Har Gar Jal | Not Certified |