Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | 20059192 | MAHMMADPUR HARA & KHAWAJA SARAI URF SAIRAIYA WSS | 390.80 | 220.10 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 15667.00 | 15667.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Tilhar | Mahmmadpur Hara | 406738 | Mahmmadpur Hara | 191 | 191 | 100 | Har Gar Jal | Not Certified |
| 2 | Shahjahanpur | Tilhar | Mahmmadpur Hara | 406739 | Babupur Khurd Urf Nagaria | 151 | 147 | 97 | Work In Progress | Not Certified |
| 3 | Shahjahanpur | Tilhar | Mahmmadpur Hara | 406740 | Patti Bakhs | 56 | 56 | 100 | Har Gar Jal | Not Certified |
| 4 | Shahjahanpur | Tilhar | Khawaja Sarai Urf Sairaiya | 406742 | Khawaja Sarai Urf Sairaiya | 162 | 162 | 100 | Har Gar Jal | Not Certified |
| 5 | Shahjahanpur | Tilhar | Khawaja Sarai Urf Sairaiya | 406743 | Raina | 172 | 168 | 98 | Work In Progress | Not Certified |