Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20059661 | JAGDISHPUR TA. KUNWARPUR, RAJJOPUR, RAMPUR SAWAI VILLAGE WATER SUPPLY SCHEME | 570.76 | 323.73 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 44400.00 | 42350.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Machhlishahr | Rajjupur | 469539 | Rajjupur | 267 | 262 | 98 | Work In Progress | Not Certified |
| 2 | Jaunpur | Machhlishahr | Rajjupur | 469540 | Babhanpur | 63 | 50 | 79 | Work In Progress | Not Certified |
| 3 | Jaunpur | Machhlishahr | Jagadishpur Ta.kunwarpur | 469541 | Dhanipur | 42 | 36 | 86 | Work In Progress | Not Certified |
| 4 | Jaunpur | Machhlishahr | Jagadishpur Ta.kunwarpur | 469542 | Jagadishpur Ta.kunwarpur | 126 | 121 | 96 | Work In Progress | Not Certified |
| 5 | Jaunpur | Machhlishahr | Jagadishpur Ta.kunwarpur | 469543 | Darabpur | 69 | 66 | 96 | Work In Progress | Not Certified |
| 6 | Jaunpur | Machhlishahr | Rampur Sawai | 469544 | Rampur Sawai | 237 | 222 | 94 | Work In Progress | Not Certified |