Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20059822 | JAMALAPUR & RANIPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 440.21 | 194.48 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | No | 0 | NA | No | 32335.00 | 26350.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mariyahun | Ranipur | 469708 | Ranipur | 47 | 47 | 100 | Har Gar Jal | Not Certified |
| 2 | Jaunpur | Mariyahun | Ranipur | 469709 | Barauli | 183 | 137 | 75 | Work In Progress | Not Certified |
| 3 | Jaunpur | Mariyahun | Jamalapur | 469710 | Jamalapur | 236 | 172 | 73 | Work In Progress | Not Certified |
| 4 | Jaunpur | Mariyahun | Jamalapur | 469711 | Chak Dost Jamalpur | 13 | 1 | 8 | Work In Progress | Not Certified |
| 5 | Jaunpur | Mariyahun | Jamalapur | 469712 | Jagdishpur | 74 | 29 | 39 | Work In Progress | Not Certified |