Scheme Details
DISTRICT
Bulandshahr
AGENCY
JMC - Kalpataru
SCHEME ID
20060342
SCHEME NAME
Talwar,Udaypur Khurd Bangar WSS
ESTIMATED COST
557.19
EXPENDITURE
235.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
51
Procured
51
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21325.00
Meter
Length Laid
18000.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Dibai | Talwar | 393812 | Udaypur Khurd Bangar | 174 | 160 | 92% | Work In Progress | Not Certified |
| 2 | Bulandshahr | Dibai | Talwar | 393813 | Talwar | 1094 | 1082 | 99% | Work In Progress | Not Certified |