Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20065266 | Aniso PWS | 317.93 | 239.93 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 13450.00 | 13450.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Bidhuna | Jalalpur Bidhuna | 420346 | Patti Ghurau | 99 | 99 | 100 | Har Gar Jal | Not Certified |
| 2 | Auraiya | Bidhuna | Anison | 420347 | Jamalpur | 114 | 114 | 100 | Har Gar Jal | Certified |
| 3 | Auraiya | Bidhuna | Anison | 420355 | Anison | 183 | 183 | 100 | Har Gar Jal | Certified |